Resource Consents at the Huntly Power Station
Resource Consents are required for a number of activities related to the operation and maintenance of the generation assets at the Huntly Power Station. Further information on Genesis Energy’s environmental responsibilities can be seen here.
Huntly Power Station Resource Consents
| Units 1 to 4 |
|
| Asset type |
Thermal generation |
| Number of resource consents |
23 |
| Status |
Operative |
| Commencement date |
March 2013 / December 1994 |
| Duration |
Range - 10 years to no expiry date (various landuse consents) |
| Regulatory authorities |
Waikato District Council; Environment Waikato |
| Unit 5 (e3p) |
|
| Asset type |
Thermal generation |
| Number of resource consents |
10 |
| Status |
Operative |
| Commencement date |
August 2001 |
| Duration |
Range - 13 and 25 years to no expiry date (landuse consent) |
| Regulatory authorities |
Waikato District Council; Environment Waikato |
| Unit 6 |
|
| Asset type |
Thermal generation |
| Number of resource consents |
2 |
| Status |
Operative |
| Commencement date |
May 2004 |
| Duration |
22 years and no expiry date (landuse consent) |
| Regulatory authorities |
Waikato District Council; Environment Waikato |