Resource Consents at Tongariro
Resource consents are required for a number of activities related to the operation and maintenance of the Tongariro Power Scheme. Genesis Energy’s Environmental Management Framework details Genesis Energy’s obligations under the RMA and its consent acquisition process.
Resource Consent
| Tongariro Power Scheme | |
|---|---|
| Asset type: | Hydro generation |
| Number of resource consents: | 56 |
| Status: | Operative, expires 2039 |
| Commencement date: | 1 December 2004 |
| Duration: | 35 years with 5 yearly review |
| Regulatory authorities: | Waikato Regional Council, Manawatu-Wanganui Regional Council, Taupo District Council, Ruapehu District Council |